Procedure and timings for an environmental permit

Procedure and timings for an environmental permit

In most cases, you need an environmental permit before you can start your project. This article provides an overview of the different steps involved in obtaining one.

This subject may seem dull and tedious, but this overview will help you form an accurate picture of what to expect when you need an environmental permit. Make the most of it.

When a permit is required

The environmental permit replaces the former building permit, environmental permit, land subdivision permit and so on. Whether you want to put up a shelter or construct an entirely new building, the environmental permit regulations apply in both cases. The size of the project makes no difference. The regulations state the following: 

“No one may, without first obtaining an environmental permit for urban development works:

• erect or place a structure;
• combine materials for a functional purpose in such a way as to create a structure;
• demolish, rebuild, renovate or extend a structure;
• …” 

There are, of course, possible exceptions. Very small-scale projects, such as laying a driveway, may be exempt. Always check whether this applies to your project. If no exemption applies, you will need an environmental permit.  

The different steps

The environmental permit application process involves several steps. The first and most important is preparing the application. During this stage, you find out what requires a permit, draw up plans with or without an architect, and provide reasons for your application. 

You then submit your application, beginning an initial 30-day period during which it must be declared complete and admissible. During this period, the authorities check whether your application is complete. Have you forgotten something, or do they need additional information? The procedure will be suspended or you will be asked to provide further information. Once the additional information has been submitted, the authorities have another 30 days to check it.  

As soon as your application is declared complete, its substantive assessment begins. This takes a maximum of 60 days for straightforward applications and a maximum of 105 or 120 days for other applications. You must receive a decision on your application within this period. These maximum time limits are often used up because of the large number of permit applications.  

A public inquiry may be held while your application is being assessed. During the inquiry, you must display a yellow notice for 30 days. During this period, local residents can view the application and submit any objections. An objection does not automatically mean your application will be refused, but it does require extra attention!  

External bodies are also asked for advice during this period. The most common consultees are the Department of Agriculture and Fisheries, the Watercourses Department, an intermunicipal heritage body, and the Agency for Nature and Forests. Companies such as Telenet and Fluvius may also be asked for advice.  

If issues arise during the substantive assessment, such as an error, an objection or a negative opinion, the application plans may still be amended. This is done by submitting a request for amendment, which allows you to change or correct certain aspects of the application. A request for amendment gives the authorities the right to extend the decision period by 60 days. If a procedural error has been made, the application period may also be extended by 60 days through an administrative loop.  

Finally, a decision on your application must be made within the time limit. It is assessed by the municipal executive committee or the provincial executive. They decide on your application based on your documents, any objections and the advice received. They also receive a final opinion from the head of the Environment Department, recommending whether or not to grant the permit. 

The decision

Has a decision been made on your application? You must display it for a further 30 days in a clearly visible place alongside the public highway. The decision must be displayed if the permit is granted, and usually also if it is refused. During this period, interested parties can lodge an appeal. They have 35 days to do so, 5 days longer than the notice must be displayed. If no appeal is lodged, you may start work under your permit.  

Accordingly, the procedure for a straightforward application takes around 30+60+35 days, excluding the preparation time, or around four months. 

For other projects, the application takes around 30 +105+ 35 days, excluding the preparation time, or around five months.  

In both cases, the procedure may be extended by a further 60 days through a request for amendment or an administrative loop. 

Would you like help with your environmental permit application? Contact a DLV adviser at info@dlv.be or call the toll-free number 0800 90 910.   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow